湖南电力 ›› 2023, Vol. 43 ›› Issue (6): 93-98.doi: 10.3969/j.issn.1008-0198.2023.06.014

• 新技术及应用 • 上一篇    下一篇

提升调频水电站AGC响应时间性能的水储协同控制策略

三梅英1, 姚洋阳2, 邱亚鸣2, 秦会会3   

  1. 1.黄河上游水电开发有限公司,青海 西宁 810000;
    2.上海明华电力科技有限公司,上海 200090;
    3.黄河上游水电开发有限公司拉西瓦发电公司,青海 贵德 811700
  • 收稿日期:2023-08-10 修回日期:2023-09-25 出版日期:2023-12-25 发布日期:2024-01-07
  • 通信作者: 姚洋阳(1991),女,工程师,主要从事电源侧涉网技术、国产化DCS改造、分布式能源自动控制方面的研究工作。
  • 作者简介:三梅英(1975),女,高级工程师,主要从事电力系统自动化方面的研究工作。
  • 基金资助:
    国家电力投资集团有限公司科技项目(KYTC2021SD04)

Collaborative Control Strategy of Hydropower and Stored Energy to Promote AGC Response Time Performance of Frequency Regulation Hydropower Plant

SAN Meiying1, YAO Yangyang2, QIU Yaming2, QIN Huihui3   

  1. 1. Huanghe Hydropower Development Co., Ltd., Xining 810000, China;
    2. Shanghai Minghua Electric Power Science & Technology Co., Ltd., Shanghai 200090, China;
    3. Laxiwa Power Generation Branch, Huanghe Hydropower Development Co., Ltd., Guide 811700, China
  • Received:2023-08-10 Revised:2023-09-25 Online:2023-12-25 Published:2024-01-07

摘要: 西北电网作为新能源装机占比最高的区域电网,其“两个细则”要求水电机组自动发电控制(automatic generation control,AGC)响应时间须小于10 s,区域内调频水电站响应时间考核问题较为严峻。以西北电网第一调频电厂某水电站为例,基于考核情况和运行特性,提出相适应的储能配置方案,研究提升AGC响应时间性能的水储协同控制策略;通过电气闸刀进行储能链路切换,重点调节所选链路机组响应时间在17 s以内的工况;在Simulink平台进行建模仿真,并在假设边界条件下进行了经济性分析。结果表明:通过水储协同,AGC响应时间性能得到明显优化,按每月减少考核440分计算,内部收益率达18.7%,能有效缓解电站AGC响应时间被考核问题严峻的现状,提升电厂经济效益。

关键词: 水储协同, AGC响应时间, 西北电网, 两个细则

Abstract: Northwest Power Grid is the regional power grid with the highest proportion of new energy installed capacity. Its “Two Articles” require that the AGC response time of hydropower units should be less than 10s. The AGC response time assessment of frequency regulation hydropower stations in the region is pretty severe. Based on the first frequency regulation hydropower power plant of Northwest Grid, the assessment and operational characteristics are analyzed. In addition, a suitable energy storage configuration scheme is proposed. Collaborative control strategy of hydropower and stored energy to promote the AGC response time performance is analyzed. The stored energy link is switched through electric break to regulate operation conditions whose AGC response time is less than 17s. Modeling and simulation are performed on Simulink platform,moreover economic analysis is carried out under hypothetical boundary conditions. The results show that through water storage collaboration, the AGC response time performance has been significantly optimized. Calculated based on a monthly reduction of 440 points, the internal rate of return reaches 18.7%, which can effectively alleviate the severe situation of AGC response time assessment in power plants and improve the economic benefits of power plants.

Key words: coordination of hydropower and stored energy, AGC response time, northwest grid, Two Articles